Anchor case

A €24M, 10,000 t/a cellulose plant — from balance to start-up.

A pharma-grade microcrystalline cellulose plant, carried by our team from process basis and cost estimate through detail engineering, procurement and construction to a verified start-up. Client, location and dates are withheld — most of our work is under NDA, and this record is published to show method, not to trade on a name.

Scope
Process basis → detail engineering → start-up
Capital cost
€24M EPC scope
Capacity
10,000 t/a pharma-grade cellulose
Our role
Process, engineering management, site, start-up

The brief

Build a pharmaceutical-grade product line at industrial capacity — and prove the economics before committing the capital.

Pharma-grade cellulose is an unforgiving product to scale: purity, particle properties and residual limits are non-negotiable, and the qualification burden means a plant that nearly meets specification is a plant that does not sell. The owner needed a defensible capital number first, then an execution route that would not quietly trade away product quality to hold the budget.

We took the process basis, closed the balance, priced the plant with a stated accuracy class, and then stayed on the project through construction and commissioning — the same engineers from first estimate to performance test.

General arrangement section drawing of the cellulose plant process building
GA section · Plant definitionLayout freeze

How it ran

  1. 01

    Process basis and balance

    Feedstock specification, product quality targets and operating cases fixed first, then a closed mass and energy balance per stream. Pharma-grade product quality set the constraint that most of the downstream design had to respect — purity and residual limits, not throughput, drove the process configuration.

  2. 02

    Techno-economic case

    CAPEX built from sized equipment and budgetary quotes with installation factors, indirects and contingency separated, and an OPEX model at realistic utilisation rather than nameplate. The €24M scope carried a stated accuracy class, which is what allowed the owner to take the decision on it.

  3. 03

    Definition and layout

    PFDs, P&IDs, equipment datasheets, electrical and instrumentation load lists, and a 3D layout checked for access, maintenance and hazardous-area zoning before drawings were frozen. Long-lead items were identified at this stage to protect the schedule later.

  4. 04

    Procurement and detail engineering

    Technical annexes and acceptance criteria written into the equipment packages, vendor documents reviewed against the process basis, and interfaces held at defined battery limits so no scope fell between suppliers.

  5. 05

    Construction and installation

    Site engineering, inspection plans, witness points and punch-list management with HSE oversight. Progress was measured against the engineering deliverable list rather than against a contractor narrative.

  6. 06

    Commissioning and verified start-up

    Pre-commissioning, water and product runs, operator training and a performance test against the contracted basis. The plant was handed over on a measured result, with deviations documented rather than absorbed.

What the project taught us

Product quality sets the plant, not capacity

At pharma grade, the purity specification decides unit operations, materials of construction and cleaning regime. Design a plant around tonnes per year first and you rebuild it around quality later.

An accuracy class is what makes a number usable

A €24M estimate means nothing without a stated class and a named contingency. Owners can carry uncertainty — they cannot carry uncertainty they were not told about.

Interfaces are where projects leak

Most of the schedule risk sat in scope splits between equipment suppliers, not inside any one package. Battery limits written early are cheaper than claims written late.

Start-up belongs to the same team

The engineers who closed the balance were on site during commissioning. That continuity is why the ramp-up was diagnosed from the design intent instead of guessed at.

3D model of the machine line used to check equipment arrangement and access
Machine line · ArrangementDetail design
Process hall during installation, with structural steel, piping and floor drainage in place
Process hall · InstallationConstruction

Client, site and product identifiers removed. Imagery is our own project material.

One case, published in full method and zero client detail. If you want the version with names and numbers, that conversation happens under an NDA — which is exactly the arrangement your own project would get.